Hello,
Even after setting it to FB closes after backup, it does not close it. Besides, I can not run backups from the planners of FB in reduced mode (in the taskbar).
Thank you for your help


Posted: Mon Jul 16, 2012 10:36 am
by Adrian (Softland)
Hi,
FBackup will close after a scheduled backup only if it was not running when the scheduler occurred.

In other words, only if the scheduler started FBackup, it will close after the backup is finished.


Posted: Mon Jul 16, 2012 10:31 pm
by mimo57
Hi,
Thank you for that answer, it is the function I want.

But my problem is that the planner opens FB, executes scheduled tasks, but once completed, the FB window remains open. I have to close by the X.

Also, I wish not to see this window FB, but just an icon in the taskbar.


Posted: Tue Jul 17, 2012 4:50 pm
by Adrian (Softland)
Hi,
In this case, you should open Backup Properties->Scheduler->Edit Properties.

In the Execute section, check the "Command line application" and "Hide window" options.